Shoreline Stadium Case (100% Solved Assignment Solution)

Shoreline Stadium Case

The G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on July 3, 2017, and be completed in time for the start of the 2020 season. A penalty clause of $250,000 per day of delay beyond April 3 is written into the contract.

Percival Young, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project.

He also said if they were successful, the prospects of future projects are bright since there is a projected renaissance in building classic ball parks with modern luxury boxes.

ASSIGNMENT

Given the information provided in he below mentioned Table, construct a network schedule for the stadium project and answer the following questions:

  1. Will the project be able to be completed by the April 3 deadline? How long will it take?
  2. What is the critical path for the project?
  3. Based on the schedule would you recommend that G&E pursue this contact? Why?

Include a one-page Gantt chart for the stadium schedule.

Technical Details For The Shoreline Baseball Stadium

For purposes of this case assume the following:

  1. The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
  2. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given as a day off.

The construction crew work Monday through Friday.

IDActivityDurationPredecessor(s)
1Baseball Stadium
2Clear stadium site70 days
3Demolish building30 days2
4Set up construction site70 days3
5Drive support piling120 days4
6Pour lower concrete bowl120 days5
7Pour main concourse120 days6
8Install playing field90 days6
9Construct upper steel bowl120 days6
10Install seats140 days9
11Build luxury boxes90 days9
12Install jumbotron30 days9
13Stadium infrastructure120 days9
14Construct steel canopy75 days10
15Light installation30 days10
16Build roof supports90 days4
17Construct roof180 days16
18Install roof tracks90 days14
19Install roof90 days17, 18
20Inspection20 days8, 11, 13, 15, 19